Dear Sefians,
What is the Maximum Dimension of the Concrete pour for Raft/ Floor Slab. Is there any IS codal reference for the max pour. I read in some of the Standard drawings prepared by few consultants that the max pour should not exceed 29m in any direction and in case if larger pour are planned a pour strip has to designed.if pour strip has to be provided, What is the design parameters that need to be considered for the the design of this joint.
Regards Jagadish |
|